Power-Plant building
Montage Kohlestaubsilos
Assembly of carbon dust silos in the power plant "Schwarze Pumpe" 2006
Assembly of two carbon dust silos
Client: AJO - tec GmbH
Construction site: Power plant "Schwarze Pumpe"
Period of assembly: April until August 2006
The silos with an aperture of 8,00m and a height of 21,00m were pre-assembled out of segments at the construction site.
The lifting of the 50,0 to. heavy silos was carried out via a 300 to. truck-mounted crane.
The welding was predominantly executed by the rod welding process.