Steelworks
Assemblies, repairs and reconstructions
... in the steel industry |
Installation of 5 tandem trestles
... in Linz, Austria 2007
Assembly of a KONTI TANDEM cold roll installation in plant VA Stahl in Linz, Österreich.
Contractor VAI Voestalpine Linz, Austria Period of assembly: June 2006 until March 2007, including commissioning |
Installation of a new exhaust gas line
... in the HKM plant in Duisburg 2001
Assembly of an exhaust gas line in the sinterplant at HKM Hüttenwerke Krupp Mannesmann in Duisburg, project HKM Leep
Period of assembly: September 2001 until March 2002. |
Montage Konverter
Installation of a steel converter in Salzgitter
In the plant Salzgitter of the client Salzgitter Flachstahl GmbH
Period of assembly: January 2007 until March 2007 Plant shutdown 21 days for container replacement Contractor SMS DEMAG |
Assembly of 3 slag silos
... in Salzgitter 2007
Period of assembly: October 2005 until May 2006
Contractor Paul Wurth Umwelttechnik, Essen |
Installation of the secondary dust removal system
... in Eisenhüttenstadt 2007
Assembly of a secondary dust removal system of the converter A and B at EKO Eisenhüttenstadt in the year 2007
Period of assembly: July 2007 until December 2007 |
Installation of a new galvanizing plant
... in Linz, Austria 2007
Installation of the galvanizing plant FVZ4 in the factory of VA Stahl in Linz, Austria
Client SUNDWIG GmbH Period of assembly: May 2006 until January 2007, including commissioning |